Manufacturing Lead Times in China — Procurement Timeline Guide

Understanding lead times is crucial for successful sourcing from China. This guide provides realistic timelines for each manufacturing stage.

Typical Lead Times by Process

ProcessTooling Lead TimeSample Lead TimeProduction (per order)
Injection Molding20-40 days7-14 days (T0/T1)2-4 weeks
CNC MachiningN/A (CAM 1-3 days)3-7 days1-3 weeks
Die Casting25-45 days10-20 days3-5 weeks
Sheet Metal10-20 days (progressive die)5-10 days2-4 weeks
Metal Stamping20-40 days (progressive)10-15 days2-4 weeks
3D PrintingN/A1-5 days3-10 days

Shipping Times from China

Total Procurement Timeline

  1. Supplier sourcing & audit: 2-4 weeks
  2. Quoting & negotiation: 1-2 weeks
  3. Tooling (if needed): 3-6 weeks
  4. Sample approval: 1-3 weeks
  5. Production: 3-5 weeks
  6. Shipping: 1-5 weeks

Total minimum: 10-12 weeks for new tooled parts. Repeat orders: 5-8 weeks.

Holiday Considerations

Chinese New Year (CNY) adds 3-6 weeks of delays (Jan-Feb). National Holiday (Oct 1-7) adds 1-2 weeks. Order before holidays to ensure production slots.